APS-Q360
550 MW hybrid in Maricopa, AZ · In queue since September 2020 · Proposed COD December 2023
550 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-12-01
APS-Q360 is a proposed 550 MW hybrid solar and battery energy storage project located in Maricopa County, Arizona. The project consists of 550 MW of solar photovoltaic generation. It is interconnected to the Arizona Public Service (APS) grid at the Delaney 500kV point of interconnection.
The project is listed in the APS interconnection queue as of September 30, 2020, with a proposed commercial operation date of December 1, 2023. The interconnection agreement (IA) for the project has been executed. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.