APS-Q362
275 MW hybrid in Pinal, NC · In queue since September 2020 · Proposed COD October 2023
275 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 1m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-01
APS-Q362 is a proposed 275 MW solar and battery hybrid project located in Pinal County, Arizona. The development project consists of 275 MW of solar generation capacity. It is listed in the Arizona Public Service interconnection queue (APS-Q) with a queue entry date of September 30, 2020, and a proposed commercial operation date of October 1, 2023. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for the proposed project is the Milligan - Casa Grande 230kV substation. The project is located in the Western region of the United States. Recent news coverage has discussed the project's potential impact on the local energy grid.
Generated from interconnection queue and public data sources
State
NC
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Milligan - Casa Grande 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN