Project APS-Q370 — Project Summary

Queue ID
APS-Q370
Capacity
309.7 MW
Technology
Wind
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q370

APS-Q370BetaActiveWindAPSLBNL

309.7 MW generation in Coconino, AZ · In queue since March 2021 · Proposed COD December 2024

309.7 MW

Capacity

1

Components

Wind

5y 2m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection

Total Duration

3y 9m

Schedule

17 months past proposed COD

Impact Study25%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-15

About

APS-Q370 is a proposed wind generation project with a total capacity of 309.7 MW, located in Coconino County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 30, 2021, and a proposed commercial operation date of December 15, 2024. Its interconnection status is currently in the Cluster Study phase.

The point of interconnection for the project is the Moenkopi-Cedar Mtn 500 kV line. The developer is listed as APS.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Coconino

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Moenkopi-Cedar Mtn 500 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.