APS-Q373
60 MW hybrid in Coconino, AZ · In queue since March 2021 · Proposed COD December 2024
60 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-12-31
APS-Q373 is a proposed 60 MW hybrid solar and battery project located in Coconino County, Arizona. The development project, consisting of 60 MW of solar power, is in the Arizona Public Service interconnection queue (APS). The project entered the queue on March 30, 2021, with a proposed commercial operation date of December 31, 2024. The interconnection agreement (IA) for the project has been executed.
The point of interconnection (POI) for APS-Q373 is a new substation off the Twin Arrows - Winslow 69kV line.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
New substation off the Twin Arrows - Winslow 69kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q373