APS-Q389
300 MW hybrid in Maricopa, AZ · In queue since March 2021 · Proposed COD November 2023
300 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 8m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
APS-Q389 is a proposed 300 MW hybrid solar and battery project located in Maricopa County, Arizona. The project consists of 300 MW of solar generation. It is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 31, 2021, and a proposed commercial operation date of November 1, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is located in the western region of the United States. The point of interconnection is the Delaney 500 kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q389