Project APS-Q423 — Project Summary

Queue ID
APS-Q423
Capacity
125 MW
Technology
Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q423

APS-Q423BetaActiveBatteryAPSLBNL

125 MW storage in Navajo, AZ · In queue since September 2021 · Proposed COD December 2025

125 MW

Capacity

1

Components

Battery

4y 8m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection

Total Duration

4y 3m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntrySep 29, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

APS-Q423 is a proposed 125 MW battery storage project located in Navajo County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue with an entry date of September 29, 2021. The proposed commercial operation date is December 31, 2025.

The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the Cholla 500kV substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Navajo

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Cholla 500kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.