APS-Q425
200 MW hybrid in Yuma, AZ · In queue since September 2021 · Proposed COD December 2024
200 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
APS-Q425 is a proposed 200 MW hybrid solar and battery project located in Yuma County, Arizona. The project, under development by Arizona Public Service (APS), consists of 200 MW of solar capacity. It is listed in the Arizona Public Service interconnection queue (APS-Q425) with an entry date of September 30, 2021, and a proposed commercial operation date of December 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The point of interconnection for APS-Q425 is the Orchard 230kV substation. This proposed project has appeared in recent news coverage regarding renewable energy development in the southwestern United States.
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Orchard 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q425