Project APS-Q427 — Project Summary

Queue ID
APS-Q427
Capacity
250 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q427

APS-Q427BetaActiveBatteryAPSLBNL

250 MW storage in Maricopa, AZ · In queue since September 2021 · Proposed COD May 2025

250 MW

Capacity

1

Components

Battery

4y 8m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection

Total Duration

3y 8m

Schedule

12 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-01

About

APS-Q427 is a proposed 250 MW battery storage project located in Maricopa County, Arizona. The project is being developed within the Arizona Public Service (APS) service area. It entered the APS interconnection queue on September 30, 2021, with a proposed commercial operation date of May 1, 2025. The point of interconnection is the Freedom 230KV Switchyard. Its interconnection status is currently in the Cluster Study phase.

The development project consists of 250 MW of battery storage capacity. It is listed in the APS interconnection queue. The project has appeared in recent news coverage regarding energy storage development in Arizona.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Maricopa

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Freedom 230KV Switchyard

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.