APS-Q437
300 MW hybrid in Maricopa, AZ · In queue since September 2021 · Proposed COD May 2021
300 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Cluster Study
IA Status
COD target: 2021
Total Duration
4y 8m
Schedule
60 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-05-24
APS-Q437 is a proposed 300 MW hybrid solar and battery project located in Maricopa County, Arizona. The project, which consists of 300 MW of solar capacity, is in the Arizona Public Service (APS) interconnection queue with a queue entry date of September 30, 2021. The proposed commercial operation date is May 24, 2021, and the interconnection status is currently in the Cluster Study phase.
The point of interconnection for the development project is the Delaney 500kV Substation. The project is listed in the West region.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500kV Substation (Q276 POI 500kV)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.