APS-Q444
60 MW hybrid in Navajo, AZ · In queue since March 2022 · Proposed COD April 2024
60 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 1m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-15
APS-Q444 is a proposed 60 MW hybrid solar and battery project located in Navajo County, Arizona. The project, interconnected with Arizona Public Service (APS), entered the APS interconnection queue on March 24, 2022, with a proposed commercial operation date of April 15, 2024.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is planned for a new 69kV switchyard to be constructed south of Highway 99 and 0.04 miles east of Highway 87 in Winslow, Arizona.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
New (to be constructed) 69kV switchyard South of Hwy 99 and .04 miles East of Hwy 87 Winslow, AZ
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q444