APS-Q458
242.25 MW generation in Navajo, AZ · In queue since March 2022 · Proposed COD December 2026
242.25 MW
Capacity
1
Components
Wind
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
APS-Q458 is a proposed wind generation project with a total capacity of 242.25 MW, located in Navajo County, Arizona. The project is being developed within the Arizona Public Service (APS) service territory. It entered the APS interconnection queue on March 30, 2022, with a proposed commercial operation date of December 31, 2026. The point of interconnection is the Cedar Mountain-Moenkopi 500 kV Line. The project's interconnection status is currently in the Cluster Study phase.
The development project consists solely of wind generation, with all 242.25 MW of capacity attributed to wind turbines. The project is listed in the West region and is currently considered active within the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Cedar Mountain-Moenkopi 500 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.