Project APS-Q475 — Project Summary

Queue ID
APS-Q475
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q475

APS-Q475BetaActiveSolarBatteryAPSLBNL

250 MW hybrid in Maricopa, AZ · In queue since March 2022 · Proposed COD December 2025

250 MW

Capacity

1

Components

Solar

4y 2m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection

Total Duration

3y 9m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

APS-Q475 is a proposed 250 MW hybrid solar and battery project located in Maricopa County, Arizona. The project consists of 250 MW of solar generation, paired with battery storage. It is listed in the Arizona Public Service (APS) interconnection queue with a queue entry date of March 31, 2022, and a proposed commercial operation date of December 31, 2025. The interconnection point is the Delaney 500kV (Q437 Gen Tie) substation. Its interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Maricopa

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Delaney 500kV (Q437 Gen Tie)

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q475