Project APS-Q497 — Project Summary

Queue ID
APS-Q497
Capacity
300 MW
Technology
Wind
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q497

APS-Q497BetaActiveWindAPSLBNL

300 MW generation in Navajo, AZ · In queue since March 2023 · Proposed COD October 2027

300 MW

Capacity

1

Components

Wind

3y 2m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 7m

Impact Study25%
Queue EntryMar 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-31

About

APS-Q497 is a proposed wind generation project with a total capacity of 300 MW. The project is located in Navajo County, Arizona, and is being developed within the Arizona Public Service (APS) service territory. It is interconnected to the Cholla-Pinnacle peak 345 kV line.

The project is listed in the Arizona Public Service interconnection queue as of March 21, 2023, with a proposed commercial operation date of October 31, 2027. Its interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Navajo

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Cholla-Pinnacle peak 345 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q497