APS-Q507
400 MW hybrid in Maricopa, AZ · In queue since March 2023 · Proposed COD June 2028
400 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
APS-Q507 is a proposed 400 MW hybrid solar and battery project located in Maricopa County, Arizona. The development project consists of 400 MW of solar generation. It is listed in the Arizona Public Service (APS) interconnection queue with a queue entry date of March 31, 2023, and a proposed commercial operation date of June 1, 2028. The project's interconnection status is currently in the Cluster Study phase, and its point of interconnection is the Komatke 230kV substation.
The project is located in the western region of the United States. The utility associated with the interconnection request is Arizona Public Service (APS).
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Komatke 230kV substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.