APS-Q524
30 MW generation in Coconino, AZ · In queue since March 2023 · Proposed COD April 2026
30 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 1m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-15
APS-Q524 is a proposed 30 MW solar generation project located in Coconino County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue with an entry date of March 31, 2023. Its proposed commercial operation date is April 15, 2026.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is at the Cataract Creek 69kV substation. The developer is listed as APS.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Cataract Creek 69kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.