APS-Q525
300 MW generation in Mohave, AZ · In queue since March 2023 · Proposed COD December 2027
300 MW
Capacity
1
Components
Wind
3y 2m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
APS-Q525 is a proposed 300 MW wind generation project located in Mohave County, Arizona. The project is being developed within the Arizona Public Service (APS) service territory. It consists of 300 MW of wind capacity.
The project is listed in the Arizona Public Service interconnection queue as of March 31, 2023, with a proposed commercial operation date of December 31, 2027. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Moenkopi - El Dorado 500kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Moenkopi - El Dorado 500kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.