APS-Q534
60 MW hybrid in Navajo, AZ · In queue since April 2023 · Proposed COD December 2026
60 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
APS-Q534 is a proposed 60 MW hybrid solar and battery project located in Navajo County, Arizona. The project consists of 60 MW of solar generation. It is listed in the Arizona Public Service (APS) interconnection queue, under queue ID APS-Q534, with an entry date of April 4, 2023. The proposed commercial operation date is December 31, 2026. The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Twin Arrows - Sunshine 69 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.