APS-Q548
145 MW hybrid in Pinal, AZ · In queue since April 2024 · Proposed COD May 2027
145 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
APS-Q548 is a proposed 145 MW hybrid solar and battery project located in Pinal County, Arizona. The development project consists of 145 MW of solar capacity. It is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of April 8, 2024, and a proposed commercial operation date of May 31, 2027. The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
32.618690, -110.625809
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q548