Project APS-Q551 — Project Summary

Queue ID
APS-Q551
Capacity
700 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q551

APS-Q551BetaActiveSolarBatteryAPSLBNL

700 MW hybrid in Coconino, AZ · In queue since April 2024 · Proposed COD May 2028

700 MW

Capacity

1

Components

Solar

2y 1m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection

Total Duration

4y 1m

Impact Study25%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

About

APS-Q551 is a proposed 700 MW hybrid solar and battery project located in Coconino County, Arizona. The project, under development by Arizona Public Service (APS), consists of 700 MW of solar generation. It is currently in the Arizona Public Service interconnection queue (APS-Q551) with an entry date of April 29, 2024.

The proposed commercial operation date (COD) for APS-Q551 is May 1, 2028. The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Navajo 500 kV Switchyard.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Coconino

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Navajo 500 kV Switchyard

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.