APS-Q553
340 MW generation in Navajo, AZ · In queue since May 2024 · Proposed COD December 2028
340 MW
Capacity
1
Components
Wind
2 years
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
APS-Q553 is a proposed 340 MW wind generation project located in Navajo County, Arizona. The project is being developed within the Arizona Public Service (APS) service territory. It entered the APS interconnection queue on May 2, 2024, with a proposed commercial operation date of December 31, 2028. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Sitgreaves substation.
The project, filed under queue ID APS-Q553, consists of 340 MW of wind generation capacity. It is listed as an active project in the interconnection queue. Recent news coverage has discussed the project's potential impact on the region's energy landscape.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Sitgreaves substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q553