APS-Q565
161 MW generation in Coconino, AZ · In queue since May 2024 · Proposed COD December 2025
161 MW
Capacity
1
Components
Wind
2 years
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
1y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
APS-Q565 is a proposed wind generation project with a total capacity of 161 MW located in Coconino County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with an entry date of May 13, 2024. The proposed commercial operation date is December 31, 2025. Its interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) is listed as Lat 35.373941, Long -111.515288. The project is located in the Western region of the United States. The developer is listed as APS.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Lat 35.373941, Long -111.515288
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q565