APS-Q568
200 MW storage in Yuma, AZ · In queue since May 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
2 years
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
APS-Q568 is a proposed 200 MW battery storage project located in Yuma County, Arizona. The project is in the Arizona Public Service (APS) interconnection queue, with an entry date of May 15, 2024. The proposed commercial operation date is June 1, 2028.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the North Gila 230kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
North Gila 230kV (32.745232, - 114.491760)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.