APS-Q572
1,300 MW generation in Riverside, CA · In queue since May 2024 · Proposed COD May 2031
1,300 MW
Capacity
1
Components
Hydro
2 years
In Queue
Cluster Study
IA Status
COD target: 2031
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-09
APS-Q572 is a proposed 1300 MW hydroelectric generation project located in Riverside County, California. The project, under development by Arizona Public Service (APS), was entered into the CAISO interconnection queue on May 15, 2024, with a proposed commercial operation date of May 9, 2031. The point of interconnection is the Delaney 500kV Switchyard. Its interconnection status is currently in the Cluster Study phase.
The project consists of 1300 MW of hydroelectric capacity. It is listed in the interconnection queue of Arizona Public Service.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500kV Swtchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q572