APS-SP106
213.75 MW hybrid in Pinal, AZ · In queue since January 2023 · Proposed COD June 2025
213.75 MW
Capacity
1
Components
Solar
3y 4m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
2y 5m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-06-01
APS-SP106 is a proposed 213.75 MW hybrid solar and battery energy storage project located in Pinal County, Arizona. The development project, consisting of 213.75 MW of solar capacity, is interconnected to the Arizona Public Service (APS) grid at the Saguaro 230kV substation.
The project is listed in the APS interconnection queue with an entry date of January 27, 2023, and a proposed commercial operation date of June 1, 2025. The interconnection agreement (IA) for the project has been executed. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Saguaro 230kV substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.