Avista-100
100 MW hybrid in Benewah, ID · In queue since September 2019 · Proposed COD December 2021
100 MW
Capacity
1
Components
Solar
6y 8m
In Queue
—
IA Status
COD target: 2021
Total Duration
2y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
Avista-100 is a proposed 100 MW hybrid solar and battery project located in Benewah County, Idaho. The project consists of 100 MW of solar generation capacity. It is listed in the Avista Utilities interconnection queue as of September 27, 2019, with a proposed commercial operation date of December 31, 2021. The point of interconnection is the Benewah 230 kV Station.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
ID
County
Benewah
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Benewah 230 kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.