Avista-103
40 MW generation in Lincoln, WA · In queue since December 2019 · Proposed COD July 2021
40 MW
Capacity
1
Components
Solar
6y 5m
In Queue
—
IA Status
COD target: 2021
Total Duration
1y 7m
Schedule
59 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-07-01
Avista-103 is a proposed 40 MW solar generation project located in Lincoln County, Washington. The project is listed in the Avista Utilities interconnection queue with an entry date of December 10, 2019, and a proposed commercial operation date of July 1, 2021. The point of interconnection is the Harrington Substation 115 kV.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Harrington Substation 115 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN