Avista-104
120 MW generation in Spokane, WA · In queue since March 2020 · Proposed COD December 2023
120 MW
Capacity
1
Components
Wind
6y 2m
In Queue
—
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
Avista-104 is a proposed wind generation project located in Spokane County, Washington, with a total capacity of 120 MW. The project is being developed by Avista Utilities and interconnected to the Benewah Substation at 230 kV.
The project is currently active in the Avista Utilities interconnection queue, with an entry date of March 2, 2020, and a proposed commercial operation date of December 31, 2023.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Benewah Substation 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-104