Project Avista-104 — Project Summary

Queue ID
Avista-104
Capacity
120 MW
Technology
Wind
Status
active
Location
Spokane, WA
Region
West
Developer
IA Status

Avista-104

Avista-104BetaActiveWindAvistaLBNL

120 MW generation in Spokane, WA · In queue since March 2020 · Proposed COD December 2023

120 MW

Capacity

1

Components

Wind

6y 2m

In Queue

IA Status

COD target: 2023

Interconnection

Total Duration

3y 9m

Schedule

28 months past proposed COD

Pre-Study0%
Queue EntryMar 2, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

About

Avista-104 is a proposed wind generation project located in Spokane County, Washington, with a total capacity of 120 MW. The project is being developed by Avista Utilities and interconnected to the Benewah Substation at 230 kV.

The project is currently active in the Avista Utilities interconnection queue, with an entry date of March 2, 2020, and a proposed commercial operation date of December 31, 2023.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Spokane

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Benewah Substation 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.