Project Avista-120 — Project Summary

Queue ID
Avista-120
Capacity
1 MW
Technology
Solar+Battery
Status
active
Location
Spokane, WA
Region
West
Developer
IA Status

Avista-120

Avista-120BetaActiveSolarBatteryAvistaLBNL

1 MW hybrid in Spokane, WA · In queue since August 2021 · Proposed COD December 2022

1 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Status

COD target: 2022

Interconnection

Total Duration

1y 4m

Schedule

42 months past proposed COD

Pre-Study0%
Queue EntryAug 19, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

About

Avista-120 is a proposed 1 MW hybrid solar and battery project located in Spokane County, Washington. The development project consists of 1 MW of solar generation capacity. It is listed in the Avista Utilities interconnection queue as of August 19, 2021, with a proposed commercial operation date of December 1, 2022.

The point of interconnection for Avista-120 is the 13.2kV Third and Hatch Feeders. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Spokane

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

13.2kV Third and Hatch Feeders

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.