Avista-120
1 MW hybrid in Spokane, WA · In queue since August 2021 · Proposed COD December 2022
1 MW
Capacity
1
Components
Solar
4y 9m
In Queue
—
IA Status
COD target: 2022
Total Duration
1y 4m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
Avista-120 is a proposed 1 MW hybrid solar and battery project located in Spokane County, Washington. The development project consists of 1 MW of solar generation capacity. It is listed in the Avista Utilities interconnection queue as of August 19, 2021, with a proposed commercial operation date of December 1, 2022.
The point of interconnection for Avista-120 is the 13.2kV Third and Hatch Feeders. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
13.2kV Third and Hatch Feeders
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-120