Avista-59
60 MW hybrid in Adams, WA · In queue since May 2018
60 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
Total Duration
8 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Commercial operation date not yet determined
Avista-59 is a proposed 60 MW solar and battery hybrid project located in Adams County, Washington. The development project consists of a 60 MW solar component. It is listed in the Avista Utilities interconnection queue as of May 23, 2018, and has an executed Interconnection Agreement (IA). The point of interconnection is the Roxboro 115 kV substation.
The project is listed in the Avista queue, which is not part of a formal ISO/RTO. The developer is Avista. The project is currently listed as active.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Roxboro 115 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.