Project Avista-60 — Project Summary

Queue ID
Avista-60
Capacity
150 MW
Technology
Solar+Battery
Status
suspended
Location
Asotin, WA
Region
West
Developer
IA Status
Suspended

Avista-60

Avista-60BetaSuspendedSolarBatteryAvistaLBNL

150 MW hybrid in Asotin, WA · In queue since June 2018 · Proposed COD September 2025

150 MW

Capacity

1

Components

Solar

7y 11m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection

Total Duration

7y 3m

Suspended38%
Queue EntryJun 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-01

About

Avista-60 is a proposed 150 MW hybrid solar and battery project located in Asotin County, Washington. The project, interconnected with Avista Utilities, entered the Avista interconnection queue on June 4, 2018, with a proposed commercial operation date of September 1, 2025. The interconnection agreement status is currently listed as suspended.

The project consists of 150 MW of solar generation capacity. The interconnection point is the Dry Creek 230 kV station. The project's overall status within the interconnection queue is also listed as suspended.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Asotin

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Dry Creek 230 kV station

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.