Avista-63
26 MW generation in Kootenai, ID · In queue since June 2018 · Proposed COD March 2028
26 MW
Capacity
1
Components
Hydro
7y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2028-03-01
Avista-63 is a proposed 26 MW hydroelectric generation project located in Kootenai County, Idaho. The project is being developed by Avista Utilities and is interconnected to the Avista Utilities grid at the Post Falls Substation. It entered the Avista interconnection queue on June 8, 2018, and has a proposed commercial operation date of March 1, 2028. The project's interconnection agreement has been executed.
The project consists of 26 MW of hydroelectric capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
ID
County
Kootenai
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Post Falls Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-63