Avista-67
80 MW generation in Adams, WA · In queue since August 2018 · Proposed COD June 2023
80 MW
Capacity
1
Components
Solar
7y 9m
In Queue
—
IA Status
COD target: 2023
Total Duration
4y 10m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-30
Avista-67 is a proposed 80 MW solar generation project located in Adams County, Washington. The project is in the Avista Utilities interconnection queue, with an entry date of August 27, 2018. The proposed commercial operation date is June 30, 2023.
The project is located in the West region and interconnects to the Lind - Warden 115 kV line. The developer is Avista. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Lind - Warden 115 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-67