Project Avista-67 — Project Summary

Queue ID
Avista-67
Capacity
80 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status

Avista-67

Avista-67BetaActiveSolarAvistaLBNL

80 MW generation in Adams, WA · In queue since August 2018 · Proposed COD June 2023

80 MW

Capacity

1

Components

Solar

7y 9m

In Queue

IA Status

COD target: 2023

Interconnection

Total Duration

4y 10m

Schedule

35 months past proposed COD

Pre-Study0%
Queue EntryAug 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-30

About

Avista-67 is a proposed 80 MW solar generation project located in Adams County, Washington. The project is in the Avista Utilities interconnection queue, with an entry date of August 27, 2018. The proposed commercial operation date is June 30, 2023.

The project is located in the West region and interconnects to the Lind - Warden 115 kV line. The developer is Avista. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Adams

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Lind - Warden 115 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.