Project Avista-71 — Project Summary

Queue ID
Avista-71
Capacity
1 MW
Technology
Solar
Status
active
Location
Lincoln, WA
Region
West
Developer
IA Status

Avista-71

Avista-71BetaActiveSolarAvistaLBNL

1 MW generation in Lincoln, WA · In queue since October 2018 · Proposed COD August 2020

1 MW

Capacity

1

Components

Solar

7y 7m

In Queue

IA Status

COD target: 2020

Interconnection

Total Duration

1y 10m

Schedule

70 months past proposed COD

Pre-Study0%
Queue EntryOct 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-08-15

About

The Avista-71 development project is a proposed 1 MW solar generation facility located in Lincoln County, Washington. The project is in the Avista Utilities interconnection queue, with an entry date of October 4, 2018. The proposed commercial operation date is August 15, 2020.

The project is currently listed as active in the interconnection queue. The point of interconnection is the Harrington Substation 115 kV.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Lincoln

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Harrington Substation 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Avista-71