Avista-80
19 MW hybrid in Spokane, WA · In queue since December 2018 · Proposed COD September 2025
19 MW
Capacity
1
Components
Solar
7y 5m
In Queue
—
IA Status
COD target: 2025
Total Duration
6y 9m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-30
Avista-80 is a proposed 19 MW hybrid solar and battery project located in Spokane County, Washington. The project, under development by Avista Utilities, consists of 19 MW of solar generation. It is listed as active in the Avista Utilities interconnection queue as of December 17, 2018, with a proposed commercial operation date of September 30, 2025. The point of interconnection is the South Fairchild Tap 115 kV.
The project is located in the West region. It is designated as a hybrid project due to its combination of solar and battery technologies. The project has appeared in recent news coverage regarding Avista's grid modernization efforts.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
South Fairchild Tap 115 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.