Project Avista-81 — Project Summary

Queue ID
Avista-81
Capacity
94 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status

Avista-81

Avista-81BetaActiveSolarAvistaLBNL

94 MW generation in Adams, WA · In queue since December 2018 · Proposed COD June 2020

94 MW

Capacity

1

Components

Solar

7y 5m

In Queue

IA Status

COD target: 2020

Interconnection

Total Duration

1y 6m

Schedule

71 months past proposed COD

Pre-Study0%
Queue EntryDec 18, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-30

About

Avista-81 is a proposed solar generation project located in Adams County, Washington, with a total capacity of 94 MW. The project is listed in the Avista Utilities interconnection queue, with an entry date of December 18, 2018. The proposed commercial operation date is June 30, 2020.

The project is interconnected to the Lind - Shawnee 115 kV line. As of the latest data, the project's status in the interconnection queue is active.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Adams

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Lind - Shawnee 115 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Avista-81