Avista-81
94 MW generation in Adams, WA · In queue since December 2018 · Proposed COD June 2020
94 MW
Capacity
1
Components
Solar
7y 5m
In Queue
—
IA Status
COD target: 2020
Total Duration
1y 6m
Schedule
71 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-06-30
Avista-81 is a proposed solar generation project located in Adams County, Washington, with a total capacity of 94 MW. The project is listed in the Avista Utilities interconnection queue, with an entry date of December 18, 2018. The proposed commercial operation date is June 30, 2020.
The project is interconnected to the Lind - Shawnee 115 kV line. As of the latest data, the project's status in the interconnection queue is active.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Lind - Shawnee 115 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-81