Project Avista-84 — Project Summary

Queue ID
Avista-84
Capacity
5 MW
Technology
Solar+Battery
Status
active
Location
Stevens, WA
Region
West
Developer
IA Status

Avista-84

Avista-84BetaActiveSolarBatteryAvistaLBNL

5 MW hybrid in Stevens, WA · In queue since April 2019 · Proposed COD December 2024

5 MW

Capacity

1

Components

Solar

7y 1m

In Queue

IA Status

COD target: 2024

Interconnection

Total Duration

5y 8m

Schedule

16 months past proposed COD

Pre-Study0%
Queue EntryApr 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

About

Avista-84 is a proposed 5 MW hybrid solar and battery project located in Stevens County, Washington. The project consists of 5 MW of solar generation. It is listed in the Avista Utilities interconnection queue with an entry date of April 17, 2019, and a proposed commercial operation date of December 31, 2024.

The project is currently listed as active in the interconnection queue. The point of interconnection is the Chewelah 13kV substation.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Stevens

Grid Region

Mountain West

Market

Developer

Utility

Avista Utilities

Entity

Avista

Service Type

Point of Interconnection

Chewelah 13kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Avista-84