Avista-84
5 MW hybrid in Stevens, WA · In queue since April 2019 · Proposed COD December 2024
5 MW
Capacity
1
Components
Solar
7y 1m
In Queue
—
IA Status
COD target: 2024
Total Duration
5y 8m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
Avista-84 is a proposed 5 MW hybrid solar and battery project located in Stevens County, Washington. The project consists of 5 MW of solar generation. It is listed in the Avista Utilities interconnection queue with an entry date of April 17, 2019, and a proposed commercial operation date of December 31, 2024.
The project is currently listed as active in the interconnection queue. The point of interconnection is the Chewelah 13kV substation.
Generated from interconnection queue and public data sources
State
WA
County
Stevens
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Chewelah 13kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-84