Avista-85
5 MW generation in Adams, WA · In queue since April 2019 · Proposed COD August 2020
5 MW
Capacity
1
Components
Solar
7y 1m
In Queue
—
IA Status
COD target: 2020
Total Duration
1y 4m
Schedule
69 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-08-31
Avista-85 is a proposed 5 MW solar generation project located in Adams County, Washington. The project is listed in the Avista Utilities interconnection queue with a queue entry date of April 17, 2019. The proposed commercial operation date is August 31, 2020.
The interconnection point of contact for Avista-85 is SOT 522. As of the latest data, the project remains in active status within the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
SOT 522
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-85