Avista-97
100 MW hybrid in Nez Perce, ID · In queue since June 2019 · Proposed COD December 2025
100 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
Avista-97 is a proposed 100 MW hybrid solar and battery energy storage project located in Nez Perce County, Idaho. The project, under development by Avista Utilities, consists of 100 MW of solar photovoltaic generation. It is interconnected to the Avista Utilities grid at the Lolo 230 kV Station.
The project entered the Avista interconnection queue on June 24, 2019, with a proposed commercial operation date of December 31, 2025. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
ID
County
Nez Perce
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Lolo 230 kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.