Avista-CS23-14
40 MW generation in Spokane, WA · In queue since April 2023 · Proposed COD June 2027
40 MW
Capacity
1
Components
Solar
3y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-30
Avista-CS23-14 is a proposed 40 MW solar generation project located in Spokane County, Washington. The project is listed in the Avista Utilities interconnection queue with a queue entry date of April 28, 2023. Its proposed commercial operation date is June 30, 2027, and the interconnection agreement has been executed. The point of interconnection is the North Fairchild Tap (115kV).
The development project consists solely of 40 MW of solar photovoltaic generation. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
North Fairchild Tap (115kV)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.