Avista-CS24-07
2 MW generation in Adams, WA · In queue since April 2024 · Proposed COD December 2024
2 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
8 months
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-10
Avista-CS24-07 is a proposed solar generation project located in Adams County, Washington, with a total capacity of 2 MW. The project is listed in the Avista Utilities interconnection queue with an entry date of April 29, 2024. Its proposed commercial operation date is December 10, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Othello 13kV substation.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Othello 13kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.