Avista-CS24-13
95 MW generation in Whitman, WA · In queue since April 2024 · Proposed COD October 2027
95 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-26
Avista-CS24-13 is a proposed 95 MW solar generation project located in Whitman County, Washington. The project is listed in the Avista Utilities interconnection queue with an entry date of April 30, 2024. Its proposed commercial operation date is October 26, 2027.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the Benewah-Thornton 230kV line. The developer is listed as Avista.
Generated from interconnection queue and public data sources
State
WA
County
Whitman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Benewah-Thornton 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-CS24-13