Avista-CS24-14
40 MW generation in Spokane, WA · In queue since April 2024 · Proposed COD June 2027
40 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
Avista-CS24-14 is a proposed solar generation project located in Spokane County, Washington, with a total capacity of 40 MW. The project, developed by Avista Utilities, consists of 40 MW of solar photovoltaic generation.
The project is currently in the Avista Utilities interconnection queue as of April 30, 2024, and has a proposed commercial operation date of June 30, 2027. Its interconnection status is listed as "Cluster Study," and the point of interconnection is the South Fairchild Tap 115kV.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
South Fairchild Tap 115kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-CS24-14