Avista-CS24-15
300 MW hybrid in Lincoln, WA · In queue since April 2024 · Proposed COD December 2027
300 MW
Capacity
1
Components
Wind
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Avista-CS24-15 is a proposed 300 MW hybrid wind and battery project located in Lincoln County, Washington. The project, developed by Avista Utilities, consists of 300 MW of wind generation. It is currently listed as active in the Avista interconnection queue, with an entry date of April 30, 2024.
The proposed commercial operation date for Avista-CS24-15 is December 31, 2027. The project's interconnection status is currently in the Cluster Study phase, and it intends to interconnect at the Bluebird Substation 230kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Bluebird Substation 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.