Avista-Q97
100 MW hybrid in Nez Perce, ID
100 MW
Capacity
1
Components
Solar
—
In Queue
Suspended
IA Status
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Avista-Q97 is a proposed 100 MW solar and battery hybrid project located in Nez Perce County, Idaho. The project, developed by Avista Utilities, consists of 100 MW of solar generation paired with battery storage. It is interconnected to the Avista Utilities grid at the Lolo 230kV Station.
The project is listed in the Avista interconnection queue as Q97. Its interconnection agreement status is currently suspended.
Generated from interconnection queue and public data sources
State
ID
County
Nez Perce
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Lolo 230kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.