Avista-TCS-14
375 MW hybrid in Garfield, WA
375 MW
Capacity
1
Components
Wind
—
In Queue
Construction
IA Status
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Avista-TCS-14 is a proposed 375 MW hybrid wind and battery project located in Garfield County, Washington. The project, developed by Avista Utilities, consists of 375 MW of wind generation capacity. It is interconnected to the Avista Utilities grid at the Dry Creek 230kV Station.
The project is currently listed as active in the Avista Utilities interconnection queue. Its interconnection agreement status is listed as "Construction". The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Garfield
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
—
Point of Interconnection
Dry Creek 230kV Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Avista-TCS-14