BHCT-BHCT G32
200 MW hybrid in Pueblo, CO · In queue since April 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-01
BHCT-BHCT G32 is a proposed 200 MW hybrid solar and battery project located in Pueblo County, Colorado. The development project, under the entity BHCT, is interconnected with Black Hills Colorado Electric. It consists of 200 MW of solar capacity.
The project is currently active in the transmission interconnection queue for the West region, having entered the queue on April 22, 2022. The proposed commercial operation date is April 1, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Burnt Mill Substation.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Service Type
—
Point of Interconnection
Burnt Mill Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.