BHCT-BHCT G38
150 MW hybrid in Pueblo, CO · In queue since August 2022 · Proposed COD December 2025
150 MW
Capacity
1
Components
Solar
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
BHCT-BHCT G38 is a proposed 150 MW hybrid solar and battery project located in Pueblo County, Colorado, within the West region. The development project, under the utility Black Hills Colorado Electric and entity BHCT, consists of 150 MW of solar capacity.
The project is currently active in the interconnection queue of an unknown ISO/RTO, having entered the queue on August 18, 2022. Its proposed commercial operation date is December 1, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Baculite Mesa Substation.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Service Type
—
Point of Interconnection
Baculite Mesa Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BHCT-BHCT G38