200 MW generation in Pueblo, CO · In queue since June 2024 · Proposed COD December 2026
200 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
BHCT-BHCT G49 is a proposed solar generation project with a total capacity of 200 MW, located in Pueblo County, Colorado. The project is being developed by BHCT and is interconnected with Black Hills Colorado Electric. It entered the transmission queue on June 12, 2024, and has a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) for the project is the 115KV Reader to Rattlesnake Butte line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Service Type
—
Point of Interconnection
115KV Reader to Rattlesnake Butte
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.