BHCT-BHCT G50
50 MW storage in Pueblo, CO · In queue since June 2024 · Proposed COD March 2026
50 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
1y 9m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
BHCT-BHCT G50 is a proposed 50 MW battery storage project located in Pueblo County, Colorado. The project, under development by Black Hills Colorado Electric, LLC, consists of a single 50 MW battery component. It is interconnected within the West region and is in the Public Service Company of Colorado (PSCo) interconnection queue, with an entry date of June 12, 2024.
The proposed commercial operation date for the project is March 1, 2026. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is at a substation, with approximate coordinates 38.3188659, -.
Generated from interconnection queue and public data sources
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
Black Hills Colorado Electric, LLC
Utility
Black Hills Colorado Electric
Entity
BHCT
Service Type
—
Point of Interconnection
a Substation, Approximate Coordinates: 38.3188659, -
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BHCT-BHCT G50