BHP-BHBE G13
300 MW generation in Custer, NE · In queue since July 2017 · Proposed COD December 2023
300 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
6y 5m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2023-12-31
The proposed BHP-BHBE G13 project is a 300 MW wind generation facility located in Custer County, Nebraska. The project is being developed by Black Hills Power (BHP) and consists of 300 MW of wind power capacity.
The project is currently active in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on July 5, 2017. The proposed commercial operation date is December 31, 2023, and an Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the West Hill - Stegall Tap.
Generated from interconnection queue and public data sources
State
NE
County
Custer
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Power
Entity
BHP
Service Type
—
Point of Interconnection
West Hill - Stegall Tap
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.